Workstreams
Onboarding to the Cohort Discovery Service requires completing three core workstreams. These can be run in parallel, though some interdependencies exist.
-
Governance
Obtain consent, complete local approvals, and conduct risk assessments.
-
Data
Extract, map to OMOP, and ETL your data to the secure environment.
-
Infrastructure
Set up your secure network area and install query retrieval software.
Interdependencies
graph LR
G1[G1: Data Controller Consent] -->|"Required before\nlive data"| I3[I3: Connect OMOP\nto Query Tool]
D1[D1: Extract Data] --> D2[D2: Map to OMOP]
D2 --> D4[D4: ETL to OMOP DB]
D4 --> I3
I1[I1: Secure Network Area] --> I2[I2: Install Query Tool]
I2 --> I3
Figure 4 — Interdependencies between tasks for onboarding to Cohort Discovery

Key rule
G1 (Data Controller Consent) must be complete before live (non-synthetic) data is connected to Cohort Discovery. D1, D2, and D3 can proceed before G1.